2009 April Accelerator Schedule

Updated March 3, 2009

Date Weekday Accelerator Hall A Hall A Hall B Hall B Hall C Hall C Priority PASS Notes
    GeV/pass/Pol Experiment GeV/mA Experiment GeV/nA Experiment GeV/mA Hall A/B/C 1-10
04/01/09 Wednesday Down  Reconfigure            HKS Install                
04/02/09 Thursday Down  Reconfigure            HKS Install                
04/03/09 Friday Down  Reconfigure            HKS Install                
04/04/09 Saturday Down  Reconfigure            HKS Install                
04/05/09 Sunday Down  Reconfigure            HKS Install                
04/06/09 Monday Down  Reconfigure            HKS Install                
04/07/09 Tuesday Down  Reconfigure            HKS Install                
04/08/09 Wednesday Down  Reconfigure            HKS Install                
04/09/09 Thursday Down  Reconfigure            HKS Install                
04/10/09 Friday Down  Reconfigure            HKS Install                
04/11/09 Saturday Down  Reconfigure            HKS Install                
04/12/09 Sunday Down  Reconfigure            HKS Install                
04/13/09 Monday Down  Reconfigure            HKS Install                
04/14/09 Tuesday Down  Reconfigure            HKS Install                
04/15/09 Wednesday Down  Reconfigure            HKS Install                
04/16/09 Thursday Down  Reconfigure            HKS Install                
04/17/09 Friday Down  Reconfigure            HKS Install                
04/18/09 Saturday Down  Reconfigure            HKS Install                
04/19/09 Sunday Down  Reconfigure            HKS Install                
04/20/09 Monday Restore              HKS Install               10  
04/21/09 Tuesday Restore              HKS Install               10  
04/22/09 Wednesday Restore              HKS Install               10  
04/23/09 Thursday 1.2  Commission   1.268/20/p   eg1-dvcs   6.068/50/p   HKS Install       A     1/5/-     10  
04/24/09 Friday 1.2  Commission   1.268/20/p   eg1-dvcs   6.068/50/p   HKS Install       A     1/5/-     10  
04/25/09 Saturday 1.2  Commission   1.268/20/p   eg1-dvcs   6.068/50/p   HKS Install       A     1/5/-     10  
04/26/09 Sunday 1.2  E05-015/E08-005   3.668/20/p   eg1-dvcs   6.068/50/p   HKS Install       A     3/5/-     10  
04/27/09 Monday 1.2  3He SSA   3.668/20/p   eg1-dvcs   6.068/50/p   HKS Install       A     3/5/-     10  
04/28/09 Tuesday 1.2  E05-015/E08-005   3.668/20/p   eg1-dvcs   6.068/50/p   HKS Install       B     3/5/-     10  
04/29/09 Wednesday 1.2  E05-015/E08-005   3.668/20/p   eg1-dvcs   6.068/50/p   HKS Install       B     3/5/-     10  
04/30/09 Thursday 1.2  E05-015/E08-005   3.668/20/p   eg1-dvcs   6.068/50/p   HKS Install       B     3/5/-     10  
Continue to May 2009