Since the 1nA cavity installation went extremely well, the beamline
from shielding wall to tagger is under vacuum already. Once the
region I chamber is installed we should have a clear shot to the
downstream devices. It is expected that the region I installation
will be done by tomorrow, Thursday.
I will keep you informed as to the exact time/day of the one night
run.
Please let me know if anything was left in a non-functioning state
so we can restore it before the beam. For example: the tagger shutter
was installed....remove it before beam...
I hope we get the right answer this time.....
Arne
--
Arne Freyberger
JLAB (Mail Stop 12H) Phone: (757) 269-6268
12000 Jefferson Avenue Pager: (757) 680-8884 freyberg@cebaf.gov
Newport News, VA 23606 Phax: (757) 269-5800 http://www.cebaf.gov/~freyberg